Start day: Oct 9, 2000
Remove rocks from site
Week ending Oct 14, 2000
No progress
Week ending Oct 21, 2000
Markings, emptied storage container
Week ending Oct 28, 2000
Removed container, string layout, port-o-potty arrives
Week ending Nov 4, 2000
Excavation, door research
Week ending Nov 11, 2000
Foundation prep, plumbers, first inspection, groundbreaking party
Week ending Nov 18, 2000
Footings poured, slab prep, gravel & sand delivered, spread
and levelled
Week ending Nov 25, 2000
Slab poured, 2nd container removed, storage tent added
Week ending Dec 2, 2000
ON HOLD until Jan 8th, 2001
Week ending Jan 13, 2001
Framing started; roof, door, skylight, airpipe research
Week ending Jan 20, 2001
Framing continues, crane for ridge beams, sheathing starts
Week ending Jan 27, 2001
Rain, rafters started
Week ending Feb 3, 2001
More framing
Week ending Feb 10, 2001
Roof rafters complete, windows and skylights arrive, re-order window
Week ending Feb 17, 2001
Skylight installation, problems, changes
Week ending Feb 24, 2001
Electricians start
Week ending Mar 3, 2001
Siding delivered, we primed 2/3 of it. Knee braces installed.
Week ending Mar 10, 2001
Siding and drywall started, shopped for pavers, ordered garage doors
Week ending Mar 17, 2001
Conduit trenches, sewer lateral, drywall tapers, bathroom fixtures installed
Week ending Mar 24, 2001
Driveway demolition and excavation, drywall complete
Week ending Mar 31, 2001
Driveway pavers started, interior paints complete
Week ending Apr 7, 2001
Driveway complete, driveway approach demolition, screwup
with city
Week ending Apr 14, 2001
Exterior paint complete, driveway approach forms in place
Week ending Apr 21, 2001
Floor epoxy-painted, pulled wire from garage to house
Week ending Apr 28, 2001
Plumbers finish, painted stem wall, street repaved
Week ending May 5, 2001
Electricians continue, window pole problems
Week ending May 12, 2001
Garage doors installed
Week ending May 19, 2001
Passed building inspection, port-o-potty gone
Week ending May 26, 2001
Painters finish garage doors, down to punchlist
Week ending June 23, 2001
Bricklayers complete retaining wall. We're done! PARTY!