Week ending February 10, 2001


Roof rafters completed, including the funky "California valley framing" for the juncture of the L roof. Roof sheathed.

Windows and skylights delivered, DaVE dutifully measures and checks all the windows, and one is the wrong size. We re-order.

This week's final view: